Fireplace Punchlist (22 items)
Last updated: about 11 years ago
To Do (14 left)
-
Wall tear down (owner)
-
Run audio and electric lines for TV and audio
-
Run audio lines, electric lines for outlet and dedicated line for fireplace (owner)
-
Gas line installed (Mickey)
-
Reinsulate wall
-
Install fireplace appliance and vent
-
Framing the chase (8' x 5' x 20.5" with fireplace 3" off floor)
-
Installing the inside components; back brick, burner, lights, logs
-
Running and testing the unit; burn off vapors (started)
-
Wire outlet for electric and audio to front of chase (owner)
-
Open building inspection (to be scheduled by owner as soon as front electric outlet box is wired)
-
Shimmy fireplace unit so it is vertically level; current angled out on top about 1/4 - 1/2" (Andrew will do when he comes to sheetrock)
-
Install the upgrade kit. Install the arched grill and lower grill (French Country Arch) - on order
-
Sheetrock the frame, corner bead two outside and 2 inside edges with Finish coats, and prime (no floor or top molding needed)
-
Final building inspection
-
Fireplace Place to show owners the basics of how the unit works.
-
Replace vinyl siding panel underneath external vent grill (owner)
-
Caulking the outside vent to seal gap between vent cover and vinly siding (Fireplace Place)
-
Drop off masonry template for stonework (Fireplace Place
-
Order mantel shelf (owner)
-
Ordering surround veneer stone (owner)
-
Punchlist for Fireplace Place